May 24 2010
passguidess compita pk0-003

Comptia PK0-003
Comptia Project+ (2009)
1Z1-225 Oracle EBS R12: Inventory and Purchasing Fundamentals
1Z1-202 Siebel 8 Consultant Exam
1Z0-257 Hyperion Financial Management 4.1 Consultant
1Z0-259 Hyperion Planning 4.1 Consultant
1Z0-262 Hyperion Planning 4.1 Administrator
1Z0-620 Siebel7.7 Analytics App.Developer Professional Core Exam
1Z0-271 Hyperion Financial Management 9.3 Administrator I&II
1Z0-272 Hyperion Planning 9.3 Administrator I&II
1Z0-273 Hyperion Financial Management 4.1 Administrator I&II
1Z0-615 Siebel 7.7 Consultant Core Exam
1Z0-630 Siebel7.7 Analytics Server Architect Professional Core Exam
1Z0-228 Peoplesoft Enterprise 9 General Ledger
1Z1-046 Orcale database 10g:Managing Orcale on Linux for DBAs
1Z0-402 Orcale Enterprise Linux:Liunx Fundamentals
1Z0-114 Oracle SOA Foundations, Adoption and Implementation
1Z0-516 Oracle EBS R12.1 General Ledger Essentials
020-222 ACSM Health/Fitness Instructor Exam
030-333 ACSM Exercise Specialist Exam
040-444 ACSM Registered Clinical Exercise Physiologist
199-01 Riverbed Certified Solutions Professional
Q&A V3.20
Question:12
You are the project manager in a matrix structure. Your project team comes from all over the
organization and many of your project team members report to several project managers besides you. There are total 89 project team members on your project that you need to communicate with – and you’ll need to communicate with the other project managers and functional managers for each resource on the project team. What type of a chart can you create to help track the reporting relationships of all your project team members in this matrix structure?
A. Project Organization Chart
B. Resource Assignment Matrix
C. Communications matrix
D. Role and responsibility matrix
Answer: A
Question:13
Brent is the project manager of the NYE Project and he has just completed the first phase of the project. Before the project may move forward the project customer must inspect the project work to determine completeness of the work so far. This activity is part of the closing the project phase.
What process will Brent and the project stakeholders do at the end of each project phase?
A. Phase gate review
B. Inspection of key results
C. Quality control
D. Verify scope
Answer: D
Question:14
You have been hired as a contract project manager for Tech Perfect Inc. The project has already been started. Sufficient details of the project have already been structured. You are working with your team for cost estimation of the project. Which of the following estimating techniques will you use for the highest degree of accuracy?
A. Parametric modeling
B. Analogous
C. Bottom-up
D. Top-down
Answer: C
Question:15
You are the project manager for the NHQ Project and are working with Patty, a junior project
manager on the project. Patty is curious about the project’s critical path and the concept of float.
Patty doesn’t understand what the critical path is. Which one of the following statements best
describes the critical path?
A. It’s the path that contains the riskiest project activities.
B. It’s the path in the project network diagram with the most important activities.
C. It’s the path in the project network diagram that reveals the earliest date the project can be
completed.
D. It’s always the one path with the least amount of float.
Answer: C
Question:16
You are the project manager of the BGY Project. A new issue has been identified in the project
and this issue could prove to be costly for the project. The issue affects Anna’s project deliverable and she is a negative stakeholder for the project. Considering these elements of the project, what type of communication would be the most effective to share this news with Anna?
A. Documented review of the issue
B. Face-to-face meeting
C. Informal presentation meeting
D. Immediate telephone call
Answer: B
Question:17
You are the project manager of the NGH Project and are predicting the costs for your project
work. You have determined that an activity in your project has the following cost attributes
assigned to it:Optimistic – $3,500; Most Likely – $7,500; Pessimistic – $12,500. What is the
amount that you’ll record for the project’s cost in the cost management plan and estimate?
A. $7666
B. $12500
C. $3500, $7500, $12500
D. $7500
Answer: A
Question:18
Which of the following types of floats are available?
Each correct answer represents a complete solution. Choose two.
A. Half float
B. Free float
C. Full float
D. Total float
Answer: B, D
Question:19
In what organizational structure is the project manager often referred to as a project coordinator or expeditor?
A. Weak matrix
B. Balanced matrix
C. Projectized
D. Strong matrix
Answer: A
Download Free Latest Examworx Certification Dumps
- Free Examworx 1z0-516
- Free Examworx 1z0-517
- Free Examworx 1z0-518
- Free Examworx 1z0-519
- Free Examworx 1z0-521
- Free Examworx passguidess 1z0-053
- Free Examworx 1Z0-535
- Free Examworx 1Z0-535
- Free Examworx 1Z0-542
- Free Examworx 1Z0-533
Comments:
(01) posted on passguidess compita pk0-003
Post a comment



great work